|
|
||||||||||||||||
|
Timber beam-end engineering repairs - Principal carrier split Click on any of the images for a larger view. |
||||||||||||||||
|
This is a principal carrier in a detached stone building, possibly 400 years old. Viewed from the lower building line the beam appeared to have sagged. The beam was carved out of an oak trunk, and a large branch came out from the cenral section of the beam. When cut and shaped this branch 'knot' couldn't be shaped into a straight line, so the carrier was cut to take into account the deflection now seen. An internal wall of brickwork was constructed at mid section at a later date because the beam has shown signs of distress. During refurbishment this wall was removed, causing the problem to resurface. |
The client wanted the room put back into its original shape, but the problem of the split was of structural concern. |
Top view of the carrier beam.
|
||||||||||||||
|
|
||||||||||||||||
|
In theory this was a simple top slot repair. The oak had turned as hard as iron, with no insect damage or fungal decay. The slot width was 32 mm wide x 2 metres long x 220 mm deep. |
||||||||||||||||
|
For reference the split was recorded on the top surface of the beam. |
||||||||||||||||
|
The result of two days of timber removal. |
||||||||||||||||
|
That's what I call hard work! |
Cleaning of the slot. |
First dry fit - bar being lowered down. |
||||||||||||||
|
Resins and bars. |
Side shutters were installed and sealed to ensure a flat resin fill to the top bar. |
First bar laid in the base of the trench. |
||||||||||||||
|
Resin pour. |
Next bar laid onto the resin and tamped down. |
Final resin pour. Total number of steel bars laid was seven with 17.3 litres of structural pouring grout. I was very pleased with the result of this installation. It turned out to be the original conception of what the beam would have looked like with the defects no longer a problem. |
||||||||||||||