Liquid damp-proof floor membranes Project 1 - treating a new concrete floor which was installed
without a |
|||||||||
|
Water
penetration and salting can be clearly seen. |
Water had pushed up a self-levelling screed. |
||||||||
|
Tanking system including plastering work completed and the wall/floor joint sealed, including discrepancies within the concrete floor. Floor then received 3 coats of epoxy resin, providing a waterproof membrane to the concrete. Finished job. |
|||||||||
|
The screed was completely removed from the floor, and a wall/floor joint was cut into the floor to form a link to the tanking system for the brickwork. |
|||||||||